Question: Cutover strategy
Q: Please explain cut over strategy procedure? Will the system golive 100% at the same time and cut the legacy system or will it be like 20% first day and 50% next day like that ?
A: Cutover strategy depends upon how the organizations design their data load strategies. Normally, you decide the sequence of Data loads for Configuration settings, Master data, Transaction data which follows whom and then you make a copy of the system as a Production system a day before and after checking the successful data loads, you go-live 100% or partial again depending upon organizational setup and policies.